The SW 66th Street bridge over I-75 in Ocala is closed until mid-June 2027; cross on SW 43rd Street Road. Also: U.S. 441 night work and I-75 work zones.
Last checked Nov. 20, 2026. This page is refreshed weekly. State projects come from the Florida Department of Transportation’s District 5 site, CFLRoads.com, its Marion County lane closures and FL511; city information from the City of Ocala’s lane and road closures page, Streets Division and downtown construction page.
The closure most drivers will notice this week is the SW 66th Street bridge over Interstate 75, which stays closed for reconstruction until mid-June 2027. FDOT’s nightly lane closures on U.S. 441 between Summerfield and Belleview have their last scheduled night Friday, Nov. 20. FDOT has not yet posted its lane closures for Thanksgiving week, and the city lists no current street closures.
Who to call
- Traffic and closures on state roads: dial 511 or visit FL511.com
- FDOT Ocala Operations (state roads in Marion County): 352-732-1338, D5-OcalaOpsInfo@dot.state.fl.us
- I-75 projects (FDOT communications team): Tom McNiff, 352-620-3005
- City streets, potholes, sidewalks: City of Ocala Streets Division, 352-351-6733, 1805 NE 30th Ave., Building 300
- City construction projects: City Engineer’s Office, Capital Projects Division, 352-629-8419
Closures this week
State roads
From FDOT’s Marion County lane closures and FL511, checked Friday, Nov. 20.
- SW 66th Street bridge over I-75: closed until mid-June 2027 for reconstruction, part of FDOT’s I-75 project from south of S.R. 44 to S.R. 200. Eastbound drivers can take State Road 200 to SW 43rd Street Road, turn right and cross I-75 on the SW 43rd Street Road bridge. Westbound drivers can go north on SW 27th Avenue to SW 42nd Street, turn left and cross the SW 43rd Street Road bridge, then turn left on NW 40th Avenue or continue to State Road 200.
- U.S. 441 (U.S. 27/U.S. 441), north of SE 178th Place in Summerfield to south of SE 62nd Avenue in Belleview: single-lane closures in both directions, 7 p.m. to 6 a.m. nightly through Friday, Nov. 20, for milling and resurfacing. Friday night is the last night FDOT has scheduled.
- State Road 40 (Silver Springs Boulevard), U.S. 441 east to SE 196 Terrace Road: resurfacing work zones, which FDOT’s statewide work zone feed lists through March 1, 2027.
The nightly southbound I-75 lane closures between south of S.R. 44 and S.R. 200 were scheduled through Thursday, Nov. 19, and are no longer on FDOT’s list. FDOT posts each week’s planned lane closures shortly before the week starts, so closures for the week of Nov. 22 are not listed yet. FL511 showed no construction or closure events in Marion County on Friday afternoon. Work zones on I-75 shift nightly; FL511 shows the lanes blocked right now.
City streets
The City of Ocala’s lane and road closures page, checked Friday, Nov. 20, lists no current closure. Its last notice, for NE Osceola Avenue at the railroad, ended Tuesday, Nov. 17. The city says closures can change because of weather or other conditions. For other city streets, call the Streets Division at 352-351-6733.
State projects under construction
The chart shows FDOT’s Marion County construction list as of early November. The table below is the list on CFLRoads.com as of Nov. 16; FDOT has since taken the I-75 resurfacing from the Sumter County line to S.R. 200 and the C.R. 484 turn lane project off its active list.
| Project | What FDOT is doing | Cost | Estimated completion |
|---|---|---|---|
| I-75, south of S.R. 44 to S.R. 200 | Auxiliary lanes and interchange improvements | $257 million | Early 2029 |
| I-75, S.R. 200 to S.R. 326 | Auxiliary lanes between interchanges, operational improvements | $242 million | Early 2029 |
| I-75 at NW 49th Street | New diverging diamond interchange, with pedestrian and bike accommodations | $59.4 million | Fall 2028 |
| I-75 northbound rest area, C.R. 484 to S.R. 200 | Rebuilding the rest area, with more car, RV and truck parking; the rest area is closed during construction | $31 million | Summer 2027 |
| I-75, S.R. 200 to north of U.S. 27 | Repaving lanes, shoulders and ramps; guardrail and curb ramps | $12.9 million | Not listed |
| U.S. 27/U.S. 441, Sumter County line to SE 62nd Avenue | Resurfacing about 8.2 miles | $8.9 million | Spring 2027 |
| S.R. 40, NE 64th Avenue east to SE 196 Terrace Road | Resurfacing, rumble strips, pedestrian upgrades at C.R. 314 | $8.7 million | Fall 2026 |
| S.R. 40, 25th Avenue to NE 64th Avenue | Resurfacing | $5.6 million | Fall 2026 |
| Silver Springs Boulevard (S.R. 40), South Pine Avenue to NE 25th Avenue | Resurfacing, curb ramps, longer turn lanes at South Pine Avenue | $5.03 million | Fall 2026 |
| I-75 in Marion and Sumter counties | Wrong-way vehicle detection on every I-75 off-ramp | $2.2 million | Summer 2026 (FDOT has not updated the estimate) |
| S.R. 200 (SW College Road) at SW 60th Avenue | Signal, lighting and marking upgrades | $1 million | Late 2026 |
At South Pine Avenue and West Silver Springs Boulevard, FDOT is lengthening the two left-turn lanes from northbound Pine to westbound Silver Springs and the right-turn lane to eastbound Silver Springs. The midblock crosswalk on South Pine Avenue near SW Broadway Street is being removed to make room, FDOT says.
City projects
The City of Ocala’s Streets Division maintains city roads, alleys, sidewalks and rights of way. Downtown has been under a multiyear construction program: the city says major downtown projects run from October 2024 until 2027, with road closure maps posted by phase on its downtown construction page. The city also posts lane closure notices as news releases on its website and Facebook page.
What this means for you
- Crossing I-75 on the south side? Plan on the SW 43rd Street Road bridge until mid-June 2027.
- Driving U.S. 441 between Summerfield and Belleview after 7 p.m. Friday? Expect a single lane in each direction until 6 a.m. Saturday.
- Traveling for Thanksgiving? Check FL511 before you go; FDOT’s lane closures for the week of Nov. 22 were not posted when this page was checked.
- Expect I-75 work zones from south of S.R. 44 to S.R. 326 through early 2029, with lane closures most nights after 8 p.m.
Related: getting around Ocala, who to call at City Hall and moving to Ocala.
Frequently asked questions
Is the SW 66th Street bridge over I-75 in Ocala closed?
Yes. FDOT closed it for reconstruction and says it will stay closed until mid-June 2027. Drivers are sent to the SW 43rd Street Road bridge instead.
When will the I-75 widening in Ocala be finished?
FDOT’s two I-75 projects in Marion County, from south of S.R. 44 to S.R. 200 and from S.R. 200 to S.R. 326, are both estimated for completion in early 2029.
When will the I-75 and NW 49th Street interchange open?
FDOT is building a diverging diamond interchange there and estimates completion in fall 2028.
Are there lane closures on I-75 in Ocala at night?
Often. FDOT posts each week’s planned I-75 lane closures in Marion County on CFLRoads.com shortly before the week starts, usually from 8 p.m. to 6 a.m. FL511.com shows the lanes blocked at any moment.
How do I check road closures in Ocala?
Dial 511 or use FL511.com for state roads, check FDOT District 5’s CFLRoads.com for weekly lane closures in Marion County, and call the City of Ocala Streets Division at 352-351-6733 for city streets.